Construction Remains on Track at both Corsica and Comino

Construction remains on track for both Corsica and Comino with significant progress on the works at Comino and activity at almost every level of Corsica.

COMINO CONSTRUCTION UPDATE 

There has been significant progress on the works at Comino, with much of the activity happening below ground level.

The under-slab drainage has been completed for half the basement, and the second half of these works will be completed during the next two weeks.

The first of the blinding slabs has been poured and is ready for the installation of the steel reinforcing to commence. 

The lift overrun and stormwater tanks have been sheet piled and are ready to be excavated. The associated pour will happen by the middle of August.

Work will soon begin on the basement slab pour – 1500 cubic metres of concrete will be poured in four sections, with two of the four sections to be completed by the end of August.

Please take a moment to take a look at our latest construction update video and watch your new home be brought to life!

WATCH CONSTRUCTION UPDATE VIDEO

CORSICA CONSTRUCTION UPDATE 

There’s been activity at almost every level of Corsica. The structural steel to the roof is almost complete, and the roof sheeting has a planned completion date of mid-August.

External finishing trades will begin on Level 6, and the scaffold will start to drop as each level is completed.

Internal trades are progressing very well, with Level 5 fully framed and roughed in. Plasterboard sheeting is set to commence this week.

External finishing trades will begin on Level 6, and the scaffold will start to drop as each level is completed.

Internal trades are progressing very well, with Level 5 fully framed and roughed in. Plasterboard sheeting is set to commence this week.

Please take a moment to take a look at our latest construction update video and watch your new home be brought to life!

WATCH CONSTRUCTION UPDATE VIDEO

When you call The Cove home you live alongside Pelican Waters Marina and with the convenience of being able to spend a day on the water with ease. Don’t miss the opportunity to experience better.

If you haven’t secured your residence at The Cove, time is running out. Enquire Now. 

Previous
Previous

February 2024 Construction Update for both Comino & Corsica

Next
Next

Construction Underway on Comino Penthouse Residences